Phase 3 (June 2017 – February 2018)

Repairs to the side chapels of our Lady and the Sacred Heart

20th – 25th February: Canon Poucin de Wouilt put his carpenter skills to the service of the community and made the support for the Very Big Book, to be used for the visits and activities related to this restoration project

11th February: Organ & Trumpet Recital celebrating completing HLF Project

7th February: Final inspection with Canon Montjean

27th January: Final touch to the kitchenette, to offer a warm welcome to all visitors

23th November: Repairs & insulation of the barrel roofs above the side chapels – improvement of the drain gutters – Repointing of the brickwork

26th October: Outside scaffolding are going down

6th October: Repairs & insulation of the barrel roofs above the side chapels – improvement of the drain gutters – Repointing of the brickwork

17th August: Views of the condition of the top of the side chapels, inside & outside – Site visit by the restoration team