2nd December: Lighting of the transept & sanctuary completed
20th October: Painting of the church and lighting of the nave and side chapels completed
15th October: Removal of the scaffolding in the nave – Final day
14th October: Removal of the scaffolding in the nave
13th October: Removal of the scaffolding in the nave
9th October: Removal of the scaffolding in the transept – your Canons at work
8th October: Removal of the scaffolding in the transept
7th October: Removal of the scaffolding in the transept
4th October: Removal of the scaffolding in the transept
29th September: Removal of the scaffolding in the transept
24th September: Removal of the scaffolding in the side chapels
23th September: Painting of the choir loft – removal of the scaffolding in the side chapels
20th September: Painting progress: the Narthex
16th September: Painting progress: the North aisle – Electricity works for the chandeliers and the new lighting design (see our fundraising appeal here for more details)
13th September: Painting progress: the North aisle
11th September: The windows of the Sacristy are now gone for restoration – view of the newly repointed wall of the Sacristy
5th September: Outside view of the church
31st August: The sample for the chandeliers is placed in the church
29th August: Painting progress: the high levels of the church are now nearly finished
10th August: Painting progress – Repair to the flashing of the roof of the baptistry
9th August: Repairs to the wall and roof of the Sacristy – Repairs to the roof of the South Aisle
5th August: Repairs to the wall and roof of the Sacristy
4th August: Repairs to the wall and roof of the Sacristy – Arrival of the sample of the new chandeliers (see here our fundraising appeal)
3rd August: Repairs to the arch windows of the transept
31st July: Painting progress: General views
29th July: Painting progress: Low levels & high levels. repairs to the arch windows of the transept & the North Nave
28th July: Sacristy repairs: in a few days, the old pointing was removed and replaced, to improve the insulation of this part of the building. Soon the windows will be removed to be restored
24th July: Painting progress: painting the nave barrel – Views of the outside without scaffolding
21st July: Painting progress: Starting painting the Nave barrel
20th July: Dismantling of the outside scaffolding
19th July: Painting progress in the transept
16th July: Painting progress in the transept – Repairs on the windows & walls – Dismantling of the outside scaffolding
14th July: Touch repairs on the walls
13th July: Painting progress: 2nd coat on the vaults – touch repairs on the walls
7th July: Painting progress: starting the 2nd coat on the vaults
6th July: Painting progress in the transept – touch repairs on the walls, which could not be done during previous projects
5th July: Painting progress in the transept – touch repairs on the East aisle windows, which could not be done during previous projects
2nd July: Painting progress: the 1st coat is halfway on the vaults below the dome
1st July: The roof of the Sanctuary is now completed – Painting progress above the confessional
30th June: Final touches on the insulation of the roofs – Painting progress in the transept
28th June: Painting progress in the transept & St Philomena’s chapel
19th June: Thanks to a generous team of parishioners, the heavy pews of the church are now facing again the main altar.
17th June: 1st Mass & 1st office in the Sanctuary since the 23rd June 2020
16th June: Sanctuary is cleared! – Scaffolding in the side chapels
15th June: Repairs & insulation of the roof – The disassembly of the scaffolding of the sanctuary is nearly finished
14th June: Repairs & insulation of the roof
11th June: Repairs & insulation of the roof – Disassembly of the scaffolding of the sanctuary
10th June: Views from the top floor of the internal scaffolding – The workers start the disassembly of the scaffolding of the sanctuary
9th June: Repairs & insulation of the roof – The floor of the scaffolding is nearly finished
8th June: Repairs & insulation of the roof – Scaffolding inside the church & views from the top of it
7th June: Repairs & insulation of the roof
4th June: Repairs & insulation of the roof
3rd June: Starting of the repairs of the barrel roof above the Sanctuary
1st June: scaffolding in the nave
24th May: Unload of the scaffolding
19th May: Internal scaffolding in the nave
18th May: Internal scaffolding in the transept
14th May: Dismantling of the scaffolding around the dome: A crane removed the beams – day 2
13th May: A light scaffolding is built inside the church for the painting of the nave – day 1
11th May: A new sanctuary lamp is put in place
6th May: Dismantling of the scaffolding around the dome: A crane removed the beams – day 1
5th May: Disassembly of the scaffolding around the dome
28th April: Painting of the ring of the dome
26th April: Painting of the Sanctuary
25th April: Light effects through the restored dome, after Vespers on the 3rd Sunday after Easter
21st April: Internal scaffolding of the dome has been removed: we could contemplate for the fist time the new painting scheme – Cleaning of marbles above the main altar
19th April: Removal of the internal scaffolding of the dome
15th April: External painting of the copper of the window – Completion of the painting of the drum of the dome – Site visit with Canon Montjean and the restoration team
13th April: Lower part of the drum of the dome – 1st coat
12th April: Painting of the dome and the sanctuary (1st coat done on the walls)
09th April: Painting of the dome and the sanctuary
07th April: Partial removal of the scaffolding of the dome
06th April: The drum is now half-painted – Internal scaffolding has been partially removed
31st March: Painting of the drum of the dome
26th March: Site visit with Canon Montjean – brand new window, made with copper imported from Canada (see pictures from 7th December for the making of the window)
25th March: The painting of the upper part of the cornice and walls of the drum started
22nd March: Fitting of the restored windows of the drum
05th March: Internal repairs to the windows of the drum
26th February: Choice of the best colours to match the original scheme of the church, to be redecorated according to its original style
17th February: Upper windows of the Sanctuary are back in place – a floor was built in preparation for the painting of the Sanctuary
9th February: Plastering of the Sanctuary
5th February: Site visit with the architect & Canon Montjean – Scaffolding inside the drum built to be able to reinstate the restored windows and finish repairs
4th February: Plastering around the lower and upper windows of the Sanctuary
3rd February: Plastering around the lower and upper windows of the Sanctuary
2nd February: Stained glass windows back in place in the Sanctuary – Plastering around the upper windows – Improvement of the lighting rod protection
1st February: Outside Scaffolding being dismantled – Progress of the inside scaffolding – Plastering of the walls
29th January: Upper Cornice restored – Plastering of the inside – Lightning rod
27th January: Gutters back in place and protection against birds – inside plastering of the walls of the sanctuary
26th January: Improvement of the lighting rod protection – The upper cornice restored
25th January: View of the inside scaffolding in the dome drum
14th January: Site visit by our architect Mark Pearce
13th January: The upper cornice of the dome is now restored – View of the inside scaffolding in the dome drum
5th January: The upper cornice of the dome is repainted in its original color
16th December: Site Visit – Brickwork repointing nearly finished – 1st stained glass windows back in place – Gutters repaired and back in place – Building repairs inside
7th December: Visit of the factory (Design Lights Stained Glass Limited) where the stained glass windows are repaired. A new glass window, made with copper, was created to match the existing ones already on the dome.
16th November: Ongoing works: Repointing brickworks & concrete repairs on the dome
4th November: Ongoing works: Repointing brickworks & concrete repairs on the dome – Your Canons on the Dome at sunset
21st October: Ongoing works: Repointing brickworks & concrete repairs on the dome – Canon Montjean and his “beloved Dome”
17th October: Ongoing works: Repointing brickworks – concrete repairs on the dome
16th October: Ongoing works: Repointing brickworks – concrete repairs on the dome
10th October: Ongoing works: Repointing brickworks – concrete repairs have started on the dome (corroding ferrous metal reinforcement)
7th October: Ongoing works: Roof repairs have started – Visit of a professional team
23rd September: Ongoing works: The windows of the dome are down for restoration
10th September: Scaffolds are now completed
09th September: ongoing works: gutters are now down for restoration
26th August: Architect’s visit
15th August: Panoramic views from the top of the scaffolds
14th August: Ongoing works
11th August: Canon Montjean’s visit
6th August: Scaffolding works – day 29
3rd August: Scaffolding works – day 26
24th July: Scaffolding works – A crane lifted the beams around the dome
20th – 23rd July: Scaffolding works – Preparation of the beams for the dome’s scaffold
20th July: The first windows are taken down for restoration
17th July: Visit of our architect, Mark Pearce (from Kepczyk Pearce Sanderson )
17th July: Scaffolding works – day 15
15th July: First pictures of the walls, after the plaster being removed to allow them to dry
14th July: Scaffolding works – day 12
10th July: Scaffolding works – day 10
9th July: Scaffolding tour
8th July: Scaffolding works – day 8
7th July: Scaffolding works – day 7
6th July: Scaffolding works – day 6
1st July: Scaffolding works – day 3
30th June: Scaffolding works – day 2
29th June: Arrival of the scaffolds for the Sanctuary
24th June: Protection of the Sanctuary and the side aisle
Presentation of HLF4 Heritage Grant
Sign up form