5th September: Outside works: repointing the brickwork, restoration of the gutters – inside works: repairs to the reinforced concrete, plastering, new toilet at the entrance of church
28th August: Outside works: repairs & insulation of the barrel roof, restoration of the gutters – inside works: repairs to the reinforced concrete, new toilet at the entrance of church
13th August: Outside works: repairs & insulation of the barrel roof above the porch, restoration of the gutters – inside works: repairs to the reinforced concrete, plastering, new toilet at the entrance of church