Restoration of the roof of the nave & the upper part of the walls, severely damaged by the rain-water leaks.
15th October: internal repairs to the walls of the nave
5th September: Outside works: repointing the brickwork, restoration of the gutters – inside works: repairs to the reinforced concrete, plastering, new toilet at the entrance of church
28th August: Outside works: repairs & insulation of the barrel roof, restoration of the gutters – inside works: repairs to the reinforced concrete, new toilet at the entrance of church
13th August: Outside works: repairs & insulation of the barrel roof above the porch, restoration of the gutters – inside works: repairs to the reinforced concrete, plastering, new toilet at the entrance of church
4th August: Outside works – repairs & insulation of the barrel roof above the porch, repointing the brickwork
23rd July: Outside works – repairs & insulation of the barrel roof, repointing the brickwork
15th July: Outside works – repairs & insulation of the barrel roof, repointing the brickwork, repairs of the gutters from 1933
1st July: Ongoing works – Damages to the walls & ceiling – brickworks
25th June: Scaffolding are now completed
17th June: Visit of Steve Foulkes, Mayor of Wirral & Canon Philip Moor, Vicar General for the Diocese of Shrewsbury
12th June: Scaffoldings are going up outside & inside
11th June: Scaffoldings are going up outside & inside – Close views of the damages to the walls
9th June: Scaffoldings are going up outside & inside – Close views of the damages to the walls
5th June: Scaffoldings are going up outside
4th June: Scaffoldings are going up outside
3rd June: Scaffoldings are going up outside